Work to repair concrete roads across Hertfordshire highlighted to councillors
Highways officials are undertaking a six-month blitz on the maintenance of 34 concrete roads across Hertfordshire.
Unlike standard asphalt roads, these older concrete roads - most often found on housing estates or industrial estates - can move or crack over time.
When the thin asphalt surface on top cracks, it leaves patches where the concrete shows through, but because the asphalt surface on the concrete road is so thin, the surface damage is usually too shallow to qualify for repair by the county council.
Earlier this year, highways chiefs drew up £700,000 plans to repair 34 of these concrete roads across the county.


On Thursday (November 12) members of the county council’s highways cabinet panel were updated on the ongoing works.
Welcoming the progress, executive member for highways Cllr Stephen Giles-Medhurst told the panel that with this work “effectively we are preventing faults for the future”.
He said it was his intention, budgets permitting, to continue this programme with more roads in the next financial year.
A report presented to the panel says that the dedicated programme enabled the council to assess similar roads together, choose the most appropriate treatment for each location and co-ordinate works more effectively.
In some cases repairs could involve micro-surfacing, which is the installation of a thin new surface and in others - where deterioration is more widespread - they involve a more substantial new surface.
Alternatively, there may be localised patching, joint or crack repairs or the use of Roadmender, where asphalt has broken away.
But according to the report, conventional resurfacing is planned for all 34 of the earmarked sites.
Delivery started in September, with the resurfacing of Hunting Gate and Spring Lane, both in Hemel Hempstead.
Updating the meeting, group manager for asset management and maintenance Chris Allen-Smith said a further seven had been completed.
He said they planned to complete most of them in December - with the vast bulk completed by Christmas - with a couple more planned in the new year.
“This programme is cracking on rapidly,” he said.
“In November we have got another 13 we should complete over the rest of this month.”